According to Bank documents, this project will provide financing to ArmPower CJSC to construct a 250MW natural gas-fired combined cycle power plant, located 10km from Yerevan. The power plant is proposed to be located on land from the Yerevan Thermal Power Plant CJSC, adjacent to the company's existing power plant.
Yerevan Thermal Power Plant CJSC is owned by the Ministry of Energy Infrastructure and Natural Resources.
Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
---|---|---|---|---|---|---|
- | - | - | - | ArmPower CSJC | Client | - |
- | - | - | - | Yerevan Thermal Power Plant CJSC | Undisclosed | - |
No contact information provided at the time of disclosure.
ACCOUNTABILITY MECHANISM OF ADB
The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main