Punjab Urban Governance and Water Supply Improvement Program (WB-P170811)

Countries
  • India
Where the impacts of the investment may be experienced.
Specific Location
Ludhiana Municipal Corporation & Amritsar Municipal Corporation (AMC)
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • World Bank (WB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Bank Risk Rating
U
Risk rating varies among banks and may refer only to the particular investment and not to the risk for the project as a whole. Projects marked 'U' have an 'Unknown' risk rating at the time of disclosure.
Voting Date
Mar 26, 2020
The estimate day the bank will vote on a proposed investment. The decision dates may change, so review updated project documents or contact the EWS team.
Borrower
Government of India
The holder of the loan, grant, or other investment.
Sectors
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, etc.
Investment Amount (USD)
$ 250.00 million
Value listed on project documents at time of disclosure. If necessary, converted to USD$. Please review updated project documents for more information.
Project Cost (USD)
$ 340.00 million
Value listed on project documents at time of disclosure. If necessary, converted to USD$. Please see updated project documentation for more information.
Primary Source

Original disclosure @ WB website

Updated in EWS Mar 6, 2020

Disclosed by Bank Sep 11, 2019


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description

According to the bank document, Amritsar and Ludhiana have piped water supply, sewerage systems and green spaces projects supported under AMRUT. Both cities are Smart Cities under the SCM. In Amritsar, this includes interventions such as BRTS corridor, piped gas, water supply, solar roofing, SMART roads, etc. Amritsar also has ongoing initiatives to strengthen e-Governance, urban planning, project management and municipal staffing, shift to double-entry based accrual accounting, implement SBM, a JICA-supported Sewerage Project and a HRIDAY scheme on conservation of culturally important public spaces. Ludhiana has ongoing urban infrastructure programs through SCM, including e-Governance, smart ICT works, placemaking, sanitation and waste management, and integrated central command control center. It includes creating a Comprehensive Environmental Management Information System and Environmental Improvement Measures for Amritsar and Ludhiana to mitigate air pollution, reduce congestion, promote non-motorized transport, promote clean fuels, improve air quality monitoring systems, promote treatment and recycling of water, increase ground water recharge by increasing pervious areas, and reduce contamination of natural drains by closing discharge points.

The World Bank aims to respond to GoP’s request to support its ongoing and planned programs in water supply in Amritsar and Ludhiana, through a holistic Program that addresses systemic issues in urban governance and finance that hinder effective and sustainable service delivery, as well as improves water infrastructure and services.

 Program interventions will target three areas of improvement:

a) Sustainable urban finances through (i) improving OSRs, (ii) development of Capital Investment Plans and strengthening of public investment management systems; (iii) establishment and operationalization of municipal asset management systems; (iv) strengthening local public financial management systems.

b) More accountable and effective urban governance through (i) establishment of performance baselines and adoption of performance targets in select service delivery areas; (ii) development and operationalization of eGovernance action plans; (iii) strengthening of municipal cadre in associated skills and competences; and (iv) introduction of social accountability tools like social audits, report cards and scorecards

c) Improved water supply services through (i) establishment of city-based ring-fenced water and wastewater entities; (ii) improved design, construction, O&M of WTPs and distribution networks, delivery of services and collection of tariffs with the support of capable private sector operators; (iii) expansion of coverage and service delivery hours through investments in distribution networks, storage networks and WTPs that use surface water sources; (iv) reduction of NRW; etc.

Investment Description
  • World Bank (WB)

Co-financing:

World Bank (250 million)

Government (90 milloin)

 

Contact Information

World Bank
Name:Balakrishna Menon Parameswaran
Designation:Lead Urban Specialist
Role:Team Leader(ADM Responsible)T
elephone No :5220+85850
Email :bmenonparameswar@worldbank.org

Name:Srinivasa Rao Podipireddy
Designation:Senior Water Supply and Sanitation Specialist
Role:Team Leader
Telephone No :5785+47662
Email :spodipireddy@worldbank.org

Name:Yarissa Lyngdoh Sommer
Designation:Sr Urban Spec.
Role:Team Leader
Telephone No :5720+13660
Email :ylyngdoh@worldbank.org

Implementing Agencies
Ludhiana Municipal Corporation
Contact :Kanwalpreet Brar
Telephone No :916164085003
Email :sanyam.aggarwal@gmail.com

Punjab Municipal Infrastructure Development Company
Contact :Ajoy Sharma
Telephone No :919646200021
Email :ajoy_khushi@yahoo.com

Amritsar Municipal Corporation (AMC)
Contact :Harbir Singh
Telephone No :91183-250233
Email :cmcasr@punjab.gov.in

 

ACCOUNTABILITY MECHANISM OF WORLD BANK

The World Bank Inspection Panel is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by a World Bank-financed project. If you submit a complaint to the Inspection Panel, they may investigate to assess whether the World Bank is following its own policies and procedures for preventing harm to people or the environment. You can contact the Inspection Panel or submit a complaint by emailing ipanel@worldbank.org. You can learn more about the Inspection Panel and how to file a complaint at: http://ewebapps.worldbank.org/apps/ip/Pages/Home.aspx.