Lao National Road 13 Improvement and Maintenance (WB-P163730)

Countries
  • Laos
Geographic location where the impacts of the investment may be experienced.
Specific Location
Xaimounkhoung Village of Vientiane Capital to Phonhong Village of Vientiane Province.
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • Asian Infrastructure Investment Bank (AIIB)
  • World Bank (WB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Approved
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
May 18, 2018
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Government of Lao PDR
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Transport
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 40.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 94.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ WB website

Updated in EWS May 11, 2023


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the bank document, the project development objective is to improve road condition, safety and climate resilience of a 58 km-section of Lao National Road No. 13 North (NR13N) from Xaimounkhoung Village of Vientiane Capital to Phonhong Village of Vientiane Province. This section links Vientiane Capital with Vangvieng and Louangphabang, major tourist destinations. The road section also runs through two districts, Naxaythong,located in the Vientiane Capital City, and Phonhong in Vientiane Province, covering about 40 villages in total.

The project is expected to improve national connectivity, access to public services, markets for the road users particularly those in Vientiane Capital and in Vientiane Province, the project will also help to reinforce regional integration and promote greater economic activity.

Proposed works on the road includes widening the road from the existing 2 lanes to 4 lanes along the first 19km (from km 12-31) and rehabilitation of 39 km ( km 31-70) of existing 2 lanes road.

The alignment of the road itself will be modified slightly at 4 locations:

1.the Houay Xaimoun Bridge at km 6+975 will be expanded from 2 to 4 lanes, with the added lanes on the left side requiring that the centerline be shifted to the left for a
distance of 200 m from each end of the bridge;

2.the Houay Xone Bridge at km 9+953 will be expanded from 2 to 4 lanes, with either one lane added to each side or 2 lanes added on the right side (the preferred option), and the preferred options requiring that the centerline be shifted to the right for a distance of 150m from each end of the bridge;

3.the Nam Houm Bridge at km19+200 will be expanded from 2 to 4 lanes, with the added lanes on the left side requiring that the centerline be shifted to the left for a distance of 200m from the south end of the bridge and 150m from the north end; and

4.the sharp curve to the right at Ban NaNga at km 25+570, where the radius of curvature will be increased from 200m to 280m to make it safe for vehicles traveling at 80km/hr

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Borrower US$ 54 million

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Lao Consulting Group Contractor -
- - - - Lao Social Research Contractor -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.
World Bank
Sombath Southivong, Holly Krambeck
Senior Infrastructure Specialist

Borrower/Client/Recipient
Angkhansada Mouangkham
Deputy Director General, External Finance Department
angkhansada@yahoo.com
 
Implementing Agencies
Ministry of Public Works and Transport
Pheng Douangngeun
Director General, Department of Roads, MPWT
pheng_dng@yahoo.com

ACCOUNTABILITY MECHANISM OF WORLD BANK

The World Bank Inspection Panel is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by a World Bank-financed project. If you submit a complaint to the Inspection Panel, they may investigate to assess whether the World Bank is following its own policies and procedures for preventing harm to people or the environment. You can contact the Inspection Panel or submit a complaint by emailing ipanel@worldbank.org. You can learn more about the Inspection Panel and how to file a complaint at: http://ewebapps.worldbank.org/apps/ip/Pages/Home.aspx.