Achiras Wind Power Project (IIC-12063-02)

Regions
  • Latin America and Caribbean
Geographic location where the impacts of the investment may be experienced.
Countries
  • Argentina
Geographic location where the impacts of the investment may be experienced.
Specific Location
Rio Cuarto Department, in Cordoba Province, Argentina
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • IDB Invest (IDBI)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Active
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
B
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jun 13, 2017
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Central Puerto Achiras S.A.U.
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 27.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Loan Amount (USD)
$ 27.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 81.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ IIC website

Updated in EWS Sep 20, 2018

Disclosed by Bank May 4, 2017


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to IIC website, the Achiras Wind Power Project consists of the construction, operation, and maintenance of a 47,25MW wind farm and related facilities, including a 132KV 16 km-long transmission line that will be located in the Rio Cuarto Department, in the southwest area of the Cordoba Province in Argentina. The Project will have positive impacts on development, such as: (i) adding 47,25MW of renewable capacity to the Argentine grid in order to diversify the energy matrix that relies mostly on hydro and thermal power generation, and representing 20% of the total installed capacity goal of non-conventional renewable energy (NCRE) by 2025, and (ii) displacing around 100,000 equivalent tons of carbon emissions per year.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

The Project total cost is estimated in US$81 million, to be financed with an IDB Group "A" Loan of approximately US$27 million. This financing will be supplemented by an IFC "A" Loan, and the participation of a local bank for local content equipment financing, and capital contributions.

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Acciona S.A. Contractor -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

No contact information provided at the time of disclosure. 

ACCOUNTABILITY MECHANISM OF IIC

The Independent Consultation and Investigation Mechanism (MICI) is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an Inter-American Development Bank (IDB) or Inter-American Investment Corporation (IIC)-funded project. If you submit a complaint to MICI, they may assist you in addressing the problems you raised through a dispute-resolution process with those implementing the project and/or through an investigation to assess whether the IDB or IIC is following its own policies for preventing or mitigating harm to people or the environment. You can submit a complaint by sending an email to MICI@iadb.org. You can learn more about the MICI and how to file a complaint at http://www.iadb.org/en/mici/mici,1752.html (in English) or http://www.iadb.org/es/mici/mici,1752.html (Spanish).

How it works

How it works