Almaty Railway Bypass (IFC-49394)

Regions
  • Europe and Central Asia
Geographic location where the impacts of the investment may be experienced.
Countries
  • Kazakhstan
Geographic location where the impacts of the investment may be experienced.
Specific Location
Kazibek Bek, Zhetygen; Talgar, Ilyisky, Karasai and Zhambyl districts; Alatou city in Almaty region
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • International Finance Corporation (IFC)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jun 30, 2025
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Kazakhstan Temir Zholy
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Infrastructure
  • Transport
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 50.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Loan Amount (USD)
$ 50.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 304.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ IFC website

Updated in EWS May 4, 2025

Disclosed by Bank Apr 28, 2025


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

As stated by the IFC, the proposed financing is for an A Loan of up to US$ 200 million to Kazakhstan Temir Zholy Joint Stock Company (KTZ JSC), national transport and logistics holding company that manages the railway infrastructure and operates freight and passenger services in the Republic of Kazakhstan (RoK).

The financing is for the construction and operation of five train stations and auxiliary structures as defined below for passenger and freight railway service of the Almaty Railroad Bypass (the “Project”) which is part of the Trans-Caspian International Transport Route and the Middle Corridor.
The project is a greenfield development with brownfield station rehabilitation components, and its footprint comprises a 300 m wide Right of Way (RoW) (i.e., 150 m on either side of the line) at the train stations, a 160 m wide RoW (80 m on either side of the line) for the construction of railway sections between the stations (including construction sites) and with a 10 m railway line footprint included for the other parts of the railway line.

The project will include construction and operation of:

(i) 75 km railway line, with a total track length of 130 km, between Kazibek Bek and Zhetygen stations, across the districts of Talgar, Ilyisky, Karasai and Zhambyl districts and Alatou city in the Almaty region;
(ii) three new stations at Sorbulak, Moyinkum and Zhana Arna, and rehabilitation of Kazibek Bek and Zhetygen stations;
(iii) two 500/220 kV substations connecting the project to 220 kV overhead lines supplied by the Kazakhstan Electricity Grid Operating Company (KEGOC);
(iv) a 73 km single-circuit 10 kV underground line that powers auxiliary systems along the entire length of the alignment, and 1.9 km 220 kV overhead transmission line connecting the substations;
(iv) auxiliary structures including 59 culverts, 13 bridges, 11 level crossings, six cattle crossings, five railway overpasses and a vehicular overpass; and
(v) depots, maintenance and servicing facilities, workers accommodation and other supporting infrastructure at the stations and diversion of 18 Overhead Transmission Lines (OHTL) which are operated by KEGOC.

Large scale earthwork activities are required (6.2 million cubic meters) and there are 14 state owned quarry sites (176.6 ha in total) identified for the abstraction of soil and sand that are mostly located outside the RoW. The distances of the quarry sites from the nearest residential areas vary between 4 km and 29 km. Crushed stone supply for track ballast and pavement base is sourced from Malaysary station, approximately 120km from the construction site. Concrete for stations and depots will be prepared on site at temporary concrete batching plants and offsite for sleepers with the closest approximately 60 km from Almaty. The rail tracks will be prefabricated and supplied by local factories. Temporary and mobile workers accommodation camps are being established by sub-contractors along the railway RoW based on the locations of ongoing construction works. KTZ commenced construction enabling works in November 2023. The Engineering, Procurement and Construction (EPC) Contractor was appointed on March 1, 2024.  The overall construction duration is estimated to be two years. At the time of project disclosure, 40% of the construction works were complete.
The new railway line is scheduled to start operating by the first quarter of 2026.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

As stated by the IFC, the Total Project cost is estimated at approximately US$304 million. IFC is expected to provide a loan package (denominated in CHF) with a maturity of 10 years, comprised of (i) up to US$50 million of IFC A loan, and (ii) mobilization of up to US$254 million from other lenders. 

Private Actors Description
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

As stated by the IFC, KTZ is a 100% subsidiary of the JSC SWF Samruk-Kazyna, a Sovereign Wealth Fund of the Government of Kazakhstan.

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
JSC "SWF Samruk-Kazyna" (SKKZ) Parent Company Finance owns JSC National Company Kazakhstan Temir Zholy Client Transport

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

General IFC Inquiries - IFC Communications:

Address: 2121 Pennsylvania Avenue, NW, Washington DC 20433
Telephone: +1 202-473-3800
Fax: +1 202-974-4384

Client - JSC National Company Kazakhstan Temir Zholy:

Aldiyar Akhmet - Senior Manager, Borrowings and Investor Relations Department
Phone: +7 (7172) 60 37 37
Email: akhmet_a@railways.kz
Address: Kazakhstan, Astana, Dinmukhamed Konaev, 6
Website: https://railways.kz

ACCESS TO INFORMATION

You can submit a request for information disclosure at: https://disclosures.ifc.org/#/inquiries

If you believe that your request for information from IFC has been unreasonably denied, or that this Policy has been interpreted incorrectly, you can submit a complaint at the link above to IFC's Access to Information Policy Advisor, who reports directly to IFC's Executive Vice President.

ACCOUNTABILITY MECHANISM OF IFC/MIGA

The Compliance Advisor Ombudsman (CAO) is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an IFC or MIGA- financed project. If you submit a complaint to the CAO, they may assist you in resolving a dispute with the company and/or investigate to assess whether the IFC is following its own policies and procedures for preventing harm to people or the environment. If you want to submit a complaint electronically, you can email the CAO at CAO@worldbankgroup.org You can learn more about the CAO and how to file a complaint at http://www.cao-ombudsman.org

How it works

How it works