Lekela Wind BOO (EBRD-49794)

Countries
  • Egypt
Geographic location where the impacts of the investment may be experienced.
Specific Location
Gulf of Suez
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • European Bank for Reconstruction and Development (EBRD)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jan 17, 2019
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Lekela Egypt Wind Power BOO SAE
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 81.43 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 325.72 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ EBRD website

Updated in EWS Feb 13, 2019

Disclosed by Bank Oct 23, 2018


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to bank documents, the investment involves provision of long-term senior debt financing of up to USD 81 million (EUR 70 million equivalent) to finance the construction of a 250 MW wind power plant located in the Gulf of Suez, approximately 30km North-West of Ras Ghareb in Egypt. The project will be one of the first privately developed utility scale wind power plants in Egypt and will support the country in increasing its renewable energy capacity.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.
Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Lekela Power B.V. Client -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Chad Canfield
Chad.Canfield@lekela.com
http://lekela.com/

ACCOUNTABILITY MECHANISM OF EBRD

The Project Complaint Mechanism (PCM) is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an European Bank for Reconstruction and Development (EBRD)-financed project. If you submit a complaint to the PCM, it may assess compliance with EBRD's own policies and procedures to prevent harm to the environment or communities or it may assist you in resolving the problem that led to the complaint through a dialogue with those implementing the project. Additionally, the PCM has the authority to recommend a project be suspended in the event that harm is imminent. You can contact the PCM at pcm@ebrd.com or you can submit a complaint online using an online form, http://www.ebrd.com/eform/pcm/complaint_form?language=en. You can learn more about the PCM and how to file a complaint at http://www.ebrd.com/work-with-us/project-finance/project-complaint-mechanism.html.

How it works

How it works