Kokshetau Water sub-project (EBRD-48413)

Countries
  • Kazakhstan
Where the impacts of the investment may be experienced.
Specific Location
Kokshetau
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • European Bank for Reconstruction and Development (EBRD)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Approved
Bank Risk Rating
B
Risk rating varies among banks and may refer only to the particular investment and not to the risk for the project as a whole. Projects marked 'U' have an 'Unknown' risk rating at the time of disclosure.
Voting Date
Jun 20, 2017
The estimate day the bank will vote on a proposed investment. The decision dates may change, so review updated project documents or contact the EWS team.
Borrower
WATER AND SEWAGE COMPANY OF THE CITY OF KOKSHETAU
The holder of the loan, grant, or other investment.
Sectors
  • Construction
  • Infrastructure
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, etc.
Investment Amount (USD)
$ 5.28 million
Value listed on project documents at time of disclosure. If necessary, converted to USD$. Please review updated project documents for more information.
Currency conversion note:
Bank reported 4.3
Converted using 2018-04-03 exchange rate.
Project Cost (USD)
$ 13.02 million
Value listed on project documents at time of disclosure. If necessary, converted to USD$. Please see updated project documentation for more information.
Currency conversion note:
Bank reported 10.6
Converted using 2018-04-03 exchange rate.
Primary Source

Original disclosure @ EBRD website

Updated in EWS Apr 5, 2018

Disclosed by Bank Apr 3, 2018


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description

This project provides technical cooperation and financing for improvements in the quality of water and water supply security in the city of Kokshetau, Akmola Oblast. This includes the modernization of the water treatment plant, and the rehabilitation of other infrastructure.

Investment Description
  • European Bank for Reconstruction and Development (EBRD)
Private Actors
  • Kokshetau Su Arnasy -- Implementing Company

The State Communal Enterprise "Kokshetau Su Arnasy", the municipal water and wastewater utility of the City, established in the 1960s, is mainly involved in: (i) water supply to 55,100 and 2,200 state and legal entities, and (ii) collection and treatment of wastewater services. The Company supplies circa 6.4 million ms of potable water annually, 70 per cent to the population and 30 per cent to legal entities, and treats 4.6 million ms of wastewater.

Contact Information

Zeinur Ismailovich Albekov,
Director GKP, Kokshetau Su Arnasy
suarnasi@mail.ru 
+7 (7162) 770078
Valikhanov street, 175 A, Kokshetau City, Akmola Oblast, 475006

ACCOUNTABILITY MECHANISM OF EBRD
The Project Complaint Mechanism (PCM) is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an European Bank for Reconstruction and Development (EBRD)-financed project. If you submit a complaint to the PCM, it may assess compliance with EBRD's own policies and procedures to prevent harm to the environment or communities or it may assist you in resolving the problem that led to the complaint through a dialogue with those implementing the project. Additionally, the PCM has the authority to recommend a project be suspended in the event that harm is imminent. You can contact the PCM at pcm@ebrd.com or you can submit a complaint online using an online form, http://www.ebrd.com/eform/pcm/complaint_form?language=en. You can learn more about the PCM and how to file a complaint at http://www.ebrd.com/work-with-us/project-finance/project-complaint-mechanism.html.