As stated by the World Bank, the Project will mainly comprise construction of a 400 kV double-circuit transmission line (approximately 260 km within Uganda) and associated substations to interconnect Uganda's power grid with regional networks. The proposed project supports the implementation of a priority connection in the East Africa region and creates conditions for grid expansion in an access-deficit country. It forms an integral part of the East Africa Power Pool (EAPP) backbone transmission grid and enhances the reliability of power interchanges with the Southern Africa Power Pool (SAPP). The proposed line also strengthens interconnections among Nile Equatorial Lake (NEL) countries. Overall, the project supports the objectives of the region's power pools (SAPP and EAPP) to optimize energy flows, maximize economic trading, increase supply security, and reduce both carbon emissions and the cost of electricity. The transmission line will help achieve benefits from increased access to electricity, sharing of natural resources, more affordable electricity prices, and improved system reliability through regional support.
The Project will comprise the following components:
(a) Component 1: Construction of approximately 260 km of 400 kV double-circuit transmission line (Wobulenxi-Masaka-Mutukula) and associated substations at Masaka and Wobulenzi (Uganda).
(b) Component 2: Environmental and Social Mitigation, supporting implementation of Environmental Management Plans (including biodiversity offsets), Resettlement Action Plans (RAP), and Livelihood Restoration Action Plans (LRAP).
(c) Component 3: Project Implementation Support and Institutional Enhancement, including detailed line design, contractor procurement, and supervision. This component will also enhance institutional capacities of relevant utilities and sector institutions for operation of integrated transmission systems and power trade, including capacity building on climate mitigation and adaptation and implementation of a gender action plan to attract, hire, promote, and retain female talent in the energy sector.
World Bank Team Leaders:
Paul Baringanire - Senior Power Engineer
Email: pbaringanire@worldbank.org
Joseph Kapika - Senior Energy Specialist
Email: jkapika@worldbank.org
ACCESS TO INFORMATION
To submit an information request for project information, you will have to create an account to access the Access to Information request form. You can learn more about this process at: https://www.worldbank.org/en/access-to-information/request-submission
ACCOUNTABILITY MECHANISM OF THE WORLD BANK
The World Bank Inspection Panel is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by a World Bank-financed project. If you submit a complaint to the Inspection Panel, they may investigate to assess whether the World Bank is following its own policies and procedures for preventing harm to people or the environment. You can contact the Inspection Panel or submit a complaint by emailing ipanel@worldbank.org. Information on how to file a complaint and a complaint request form are available at: https://www.inspectionpanel.org/how-to-file-complaint