Cameroon - Programme for Unlocking and Connectivity of Cross-Border Economic Basins in the East Region of Cameroon – Phase 1 (AFDB-P-CM-DB0-026)

Regions
  • Africa
Geographic location where the impacts of the investment may be experienced.
Countries
  • Cameroon
Geographic location where the impacts of the investment may be experienced.
Specific Location
National Road No. 10 (East Region of Cameroon)
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • African Development Bank (AFDB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Approved
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Feb 17, 2026
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Government of Cameroon - Ministry of Public Works
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Infrastructure
  • Transport
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 361.22 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 361.22 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ AFDB website

Updated in EWS Jul 30, 2026


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the Bank’s website, the Programme for Unlocking and Connectivity of Cross-Border Economic Basins in the East Region of Cameroon – Phase 1 focuses on the upgrading and paving of the Ngoura II–Yokadouma road section over a length of 156 km along National Road No. 10, a strategic corridor linking Cameroon to the Central African Republic and the Republic of Congo. The total cost of the project amounts to EUR 309.93 million. The project is fully financed by the African Development Bank through a sovereign loan from the Bank window, while the Government of Cameroon covers taxes, customs duties, security arrangements, and in-kind contributions related to project implementation. The project forms part of a broader regional connectivity programme aimed at strengthening cross-border trade corridors and economic integration in Central Africa.

The objective of the project is to contribute to the internal and external unlocking of Cameroon’s eastern territory, strengthen sustainable private investments, and promote industrialization through the development of high-potential local and regional value chains. At sector level, the project seeks to improve transport service levels, logistics performance, and climate resilience along the Batouri–Ngoura II–Yokadouma–Moloundou–Congo border corridor. By rehabilitating a critical road link and delivering complementary infrastructure, skills development, and institutional support, the project aims to reduce transport costs and travel time, enhance road safety, facilitate access to markets for agricultural producers, and support regional integration in line with the African Continental Free Trade Area.

The direct beneficiary of the project is the Government of Cameroon through the Ministry of Public Works, which will benefit from improved transport infrastructure and strengthened institutional capacity. Indirect beneficiaries include an estimated population of over 320,000 people living in the project’s zone of influence across the Kadey and Boumba-et-Ngoko departments, including women, youth, refugees, and vulnerable groups. Additional beneficiaries include farmers, agro-processors, traders, transport operators, forest and mining sector actors, and cross-border traders who will benefit from improved mobility, reduced logistics costs, and better access to markets and services. At regional level, communities and economic actors in neighboring Central African Republic and Republic of Congo will also benefit from enhanced connectivity and trade facilitation along the corridor.

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

Environmental Category: [1] High Risk

Given the nature of the PDCBET activities, notably the construction of a new 156 km road and a 195 m bridge over the Kadey River, and the sensitivity of the programme implementation area, as well as the negative E&S risks and impacts that may result, the categorical classification corresponds to Category 1 of E&S risk in accordance with the provisions of the Bank’s ISS. This is due to the environmental and social risks and impacts inherent in the proposed activities, as well as the significant risks of involuntary resettlement of populations that the programme implementation may entail.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

The total cost of the project amounts to EUR 309.93 million. The project is fully financed by the African Development Bank through a sovereign loan from the Bank window, while the Government of Cameroon covers taxes, customs duties, security arrangements, and in-kind contributions related to project implementation.

Financial Instrument: Project (Loan)
Commitments (UA): 266,134,849
Conversion Rate USD (2026-02-17): 1,35728
Commitments (USD): 361,219,507.90


Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Name: Olaya Dègnon Cestmir Albé HOUSSOU
Email: a.houssou@afdb.org

ACCESS TO INFORMATION

You can submit an information request for project information at: https://www.afdb.org/en/disclosure-and-access-to-information/request-for-documents. Under the AfDBs Disclosure and Access to Information policy, if you feel the Bank has omitted to publish information or your request for information is unreasonably denied, you can file an appeal at https://www.afdb.org/en/disclosure-and-access-to-information/appeals-process.

ACCOUNTABILITY MECHANISM OF AfDB

The Independent Review Mechanism (IRM), which is administered by the Compliance Review and Mediation Unit (CRMU), is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an African Development Bank (AfDB)-financed project. If you submit a complaint to the IRM, it may assist you by either seeking to address your problems by facilitating a dispute resolution dialogue between you and those implementing the project and/or investigating whether the AfDB complied with its policies to prevent environmental and social harms. You can submit a complaint electronically by emailing crmuinfo@afdb.org, b.kargougou@afdb.org, b.fall@afdb.org, and/or s.toure@afdb.org. You can learn more about the IRM and how to file a complaint at: https://www.afdb.org/en/independent-review-mechanism/

How it works

How it works