Jilamito Hydroelectric Project (DFC-JILAMITO)

Countries
  • Honduras
Where the impacts of the investment may be experienced.
Specific Location
Mezapita, Municipio de Arizona, Atlántida
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • US International Development Finance Corporation (DFC)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Bank Risk Rating
A
Risk rating varies among banks and may refer only to the particular investment and not to the risk for the project as a whole. Projects marked 'U' have an 'Unknown' risk rating at the time of disclosure.
Borrower
INGELSA
The holder of the loan, grant, or other investment.
Sectors
  • Hydropower
The service or industry focus of the investment. A project can have several sectors.
Investment Amount (USD)
Not Disclosed
When disclosed, the bank did not provide this value. Please review updated project documents for more information.
Primary Source

Original disclosure @ DFC website

Updated in EWS Jul 31, 2020

Disclosed by Bank Apr 11, 2019


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description

The Project involves the construction and operations of a 14.8 MW hydropower facility on the Jilamito River, a tributary of the Lean River. Two small diversion weirs (one on the main branch of the Jilamito River and one on a smaller tributary) will be used to route the water to a settling pond where large sediments will be removed. The water will then be channeled through a low-pressure tunnel (~200 m) and pipeline (~1.2 km) to a surge tank that flows into a high-pressure penstock (~2.5 km) that leads to the power house where the turbines and generators will be housed. After passing through the turbines the water will be returned to the adjacent Los Olivios River (which re-joins the Jilamito River ~1 km downstream of the powerhouse). In addition to the main project components the following infrastructure will be required to help construct and operate the Project:
- A heavy-lift skyline cable system from powerhouse to the upper basin (~2 km);
- A new 10.5 km, 34.5kV overhead transmission line (OHL) from the Jilamito powerhouse to the Lean switching station where it will connect into the existing regional transmission system;
- One new substation (at the powerhouse) and switching station (Lean);
- A new 7.5 km access road from the nearby town of Mezapita to the Project site, and internal access roads to link the powerhouse with the upper weir sites;
- Borrow pits for the road construction;
- Concrete aggregate quarries and aggregate crushing / processing plant which is located ~60 km from the Project site in Santa Ana, Municipality de la Masica, Atlántida;
- Three material dump sites;
- General supporting infrastructure including: waste management facilities, sanitation facilities, a medical center, satellite communication equipment, and temporary generators; and
- Worker accommodation (located in Mezapita), and a mountaintop workers’ camp (for approximately 50-70 workers). This camp will be located ~50 meters downstream of the surge tank. The construction and commissioning works are expected to be completed within 40-months from start of site preparatory work.

Investment Description
  • US International Development Finance Corporation (DFC)

There wasn't any Funding information available at the moment of the snapshot.

Contact Information

Not available