The Gambia Water and Sanitation Project (WB-P513113)

Regions
  • Africa
Geographic location where the impacts of the investment may be experienced.
Countries
  • Gambia
Geographic location where the impacts of the investment may be experienced.
Specific Location
Greater Banjul Area (GBA) region (Banjul, Kanifing, and Brikama)
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • World Bank (WB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Sep 25, 2026
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Government of Gambia - National Water and Electricity Company Limited (NAWEC)
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Construction
  • Infrastructure
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Grant
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 30.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 40.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ WB website

Updated in EWS Sep 14, 2026

Disclosed by Bank Nov 21, 2025


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the Bank’s website, the Project Development Objective (PDO) is to improve access to water and sanitation services in selected regions of The Gambia and strengthen the operational and financial performance of the Water Company.

The water supply and sanitation services in The Gambia are currently facing a significant crisis due to ongoing challenges in achieving the Sustainable Development Goals (SDGs). According to the 2023 Joint Monitoring Programme (JMP) report, only 48% of the population has access to safely managed water services, with 68% access in urban areas compared to just 12% in rural areas. Access to basic sanitation services is also a major concern, as only 28% of the population has access to safely managed sanitation, while 15% still practice open defecation, particularly in rural regions. Additionally, the country lacks adequate wastewater treatment, with about 80% of wastewater improperly managed, leading to groundwater contamination and posing significant public health risks.

Three key localities in the Greater Banjul Area (GBA) - Banjul, Kanifing, and Brikama - are home to approximately 63% of the country's population. The National Water and Electricity Company (NAWEC) currently produces 139,000 cubic meters of water daily, which is insufficient to meet the demand. The GBA mainly relies on boreholes that draw water from a sub-shallow aquifer; however, this water source is vulnerable to contamination from untreated sewage and saltwater intrusion caused by rising sea levels related to climate change.

The Gambia Water and Sanitation Project (WASAP) aims to support the government's efforts to address the crisis in water and sanitation services in the Greater Banjul Area (GBA) region. This operation includes a series of activities organized into four mutually reinforcing components, which are summarized below:
- Component 1: Improving Access to Urban Drinking Water Services (US$14 million)
- Component 2: Improving Access to Sanitation Services ($18.0 million)
Component 2.1: Urban Sanitation (16.5 million)
* Emergency wastewater management ($5.0 million)
* Expansion of Kotu Wastewater System (US$3.2 million)
* Construction of a Fecal Sludge Treatment Plant ($8.3 million)
Component 2.2: Rural Sanitation Development ($1.5 million)
* Construction of Safely Managed Latrines in Targeted Rural Areas ($0.9 million)
* Development of a National Sanitation Master Plan (US$0.6 M)
- Component 3. Institutional Reform and Capacity Building for Sustainable Water Services ($6.0 million)
* Support to sector reform and NAWEC operational and financial efficacy improvement ($3.0 million)
* Supporting transboundary cooperation on the Senegal-Mauritanian Aquifer Basin ($0.5 million)
* Enhancing water resources monitoring and conservation ($2.5 million)
- Component 4. Project management: ($2 million)
- Component 5. Contingent Emergency Response Component (CERC) * Component 5 CERC $0 million
TOTAL: $30 million

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

The project’s environmental risk rating is Substantial. Key identified environmental risks and potential adverse impacts include vegetation clearing, habitat disturbance, biodiversity impacts, noise and dust emissions, soil and water contamination from wastewater, sludge, chemicals. Construction activities may also lead to Occupational Health and Safety (OHS) risks—such as injuries and accidents during construction and equipment installation— alongside community health and safety concerns as well as operational risks related to sludge management, chemicals handling, and accidental releases.

The project social risk rating is Substantial. Component 2 involves enhancements to sanitation services, including urban efforts like Emergency Wastewater Management and a Fecal Sludge Treatment Plant, as well as rural sanitation development. Component 3 aims to improve urban access to drinking water through projects centered on water supply infrastructure. Primary risks and adverse impacts are expected to include land acquisition, land use restrictions, involuntary resettlement. There is also a potential for opposition to component 2, particularly concerning the fecal sludge treatment plant, due to perceptions of fecal waste and concerns regarding proximity to communities. To a large extent, the risk of conflict may increase if community engagement is not ensured in managing site selection, incidents or accidents, community and worker grievances, and issues related to abuse, exploitation, and sexual harassment.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Total Project Cost: US$ 40.00 million
IDA Grant: US$ 30.00 million

Private Actors Description
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

The National Water and Electricity Corporation (NAWEC) is the primary state-owned utility company in The Gambia responsible for the generation, transmission, and distribution of electricity, water, and sewerage services.

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - NATIONAL WATER AND ELECTRICITY COMPANY LTD (NAWEC) Client -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

CONTACT POINT - World Bank

Task Team Leader: Sylvestre Bea
Title: Senior Water Specialist
Email: sbea@worldbank.org

ACCESS TO INFORMATION

To submit an information request for project information, you will have to create an account to access the Access to Information request form. You can learn more about this process at: https://www.worldbank.org/en/access-to-information/request-submission

ACCOUNTABILITY MECHANISM OF THE WORLD BANK

The World Bank Inspection Panel is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by a World Bank-financed project. If you submit a complaint to the Inspection Panel, they may investigate to assess whether the World Bank is following its own policies and procedures for preventing harm to people or the environment. You can contact the Inspection Panel or submit a complaint by emailing ipanel@worldbank.org. Information on how to file a complaint and a complaint request form are available at: https://www.inspectionpanel.org/how-to-file-complaint

How it works

How it works