Strategic Irrigation Modernization and Urgent Rehabilitation Project (WB-P157585)

Countries
  • Indonesia
Geographic location where the impacts of the investment may be experienced.
Specific Location
Java, Sumatra, Kalimantan, Sulawesi and NTB.
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • World Bank (WB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
B
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Borrower
Government of Indonesia
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Infrastructure
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Amount (USD)
$ 250.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 578.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ WB website

Updated in EWS Feb 27, 2018


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the bank website,the project objective is to improve irrigation services and strengthen management of irrigation schemes in selected areas. This objective will be achieved through rehabilitation and modernization of irrigation systems; institutional strengthening and improved management, operation and maintenance of these systems. The project will support the rehabilitation of at least 100,000 hectares of irrigated command area. The project has 4 components:

Component A: Urgent Rehabilitation and Infrastructure Improvements, The Government has identified a preliminary list of 41 irrigation schemes, with a total of 335,268 hectares, spread across 11 provinces and 12 balais or river territories.

Component B: Strategic Infrastructure Modernization focus on Jatiluhur Irrigation Scheme, which is served by the Citarum River in Java

Component C: Modernization of Management Systems

Component D: Institutional Modernization and Empowerment

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Co-financed by

Asian Infrastructure Investment Bank US$ 250 million

Government of Indonesia US$ 78 million


Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.
World Bank
Contact:Marcus J. Wishart
Title:Sr Water Resources Mgmt. Spec.
Contact:Cuong Hung Pham
Title:Sr Water Resources Spec.
 
Borrower/Client/Recipient
Name:Republic of Indonesia
Contact:Mr. Robert Pakpahan
Title:Director General of Budget Financing and Risk Management
Email:robert@kemenkeu.go.id
 
Implementing Agencies
Name:Ministry of Public Works (DG Water Resources)
Contact:Ir. Mudjiadi
Title:Director General of Water Resources
Email:dirjensda@pu.go.id
 

ACCOUNTABILITY MECHANISM OF WORLD BANK

The World Bank Inspection Panel is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by a World Bank-financed project.  If you submit a complaint to the Inspection Panel, they may investigate to assess whether the World Bank is following its own policies and procedures for preventing harm to people or the environment. You can contact the Inspection Panel or submit a complaint by emailing ipanel@worldbank.org. You can learn more about the Inspection Panel and how to file a complaint at: http://ewebapps.worldbank.org/apps/ip/Pages/Home.aspx.

How it works

How it works