According to the bank document, The proposed early disclosure covers an application for MIGA guarantees in support of equity, quasi-equity and/or shareholder loan investments by Shanghai SUS Environment Co., Ltd. and non-shareholder loans and a related interest rate swap to be provided by lenders yet to be identified to "SUS ENVIRONMENT SAMARKAND" FE LLC (the Project Enterprise). The investments would support the development, financing, construction, ownership and operation of a waste-to-energy facility in the Samarkand region of Uzbekistan (the Project). MIGA guarantees are expected to be for up to USD 316.75 million against the risks of Transfer Restriction, Expropriation, War and Civil Disturbance, and Breach of Contract, with tenors of up to 20 years for equity-related investments and up to 14 years for debt and swap investments.
The Project comprises a waste-to-energy plant with a net generation capacity of approximately 50 MW and municipal solid waste processing capacity of 1,500 tons per day. The facility is expected to process approximately 500,000 tons of municipal solid waste annually and generate approximately 371 GWh of electricity per year. Associated infrastructure includes grid interconnection facilities, water supply systems and other ancillary infrastructure. Construction commenced in July 2025, and commercial operations are currently targeted for July 2027.
Guangzhou WeTech Engineering Co., Ltd. : will be responsible for the Feasibility Study Report (“FSR”) and the preliminary design of the Project.
BEZOPASNOST' I KONTROL'" (“BIK”) : BIK is engaged by ERM to conduct environmental and social baseline survey, stakeholder engagement during the scoping and ESIA phases
| Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
|---|---|---|---|---|---|---|
| Shanghai SUS Environment Co., Ltd. | Client | - | contracts with | ERM: Environmental Resources Management | Contractor | - |
| Shanghai SUS Environment Co., Ltd. | Client | Energy | contracts with | Shandong Zijian Construction Group Co., Ltd. | Contractor | Construction |
No contact information was provided at the time of disclosure.
ACCESS TO INFORMATION
You can submit a request for information disclosure at: https://www.miga.org/contact/access_to_information
You can also request general information about MIGA and for information on guarantees by emailing: migainquiry@worldbank.org
ACCOUNTABILITY MECHANISM OF IFC/MIGA
The Compliance Advisor Ombudsman (CAO) is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an IFC or MIGA- financed project. If you submit a complaint to the CAO, they may assist you in resolving a dispute with the company and/or investigate to assess whether the IFC is following its own policies and procedures for preventing harm to people or the environment. If you want to submit a complaint electronically, you can email the CAO at CAO@worldbankgroup.org. You can learn more about the CAO and how to file a complaint at http://www.cao-ombudsman.org