According to the bank, IFC is considering up to US$20million A Loan and mobilization provided under IFC’s Managed Co-Lending Portfolio Program of up to US$70million to finance the construction, operation, and maintenance of total 138km of 110kV regional transmission lines in the department of La Guajira, Colombia (the “Project”).
The project involves the construction of two 110kV transmission lines, one of about 76.5 km length between Riohacha and Maicao and another of about 62 km length between Riohacha and Cuestecitas, and the refurbishment of three existing substations at Riohacha, Maicao, and Cuestecitas. There will be no expansion of the footprint of the substations.
Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
---|---|---|---|---|---|---|
- | - | - | - | Ashmore Management Company Colombia SAS | Client | - |
- | - | - | - | Consorcio CDEM | Contractor | - |
- | - | - | - | Elecnorte Andino SL | Client | - |
- | - | - | - | Montajes Morelco S.A. | Contractor | - |
ACCOUNTABILITY MECHANISM OF IFC
The Compliance Advisor Ombudsman (CAO) is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an IFC or MIGA- financed project. If you submit a complaint to the CAO, they may assist you in resolving a dispute with the company and/or investigate to assess whether the IFC is following its own policies and procedures for preventing harm to people or the environment. If you want to submit a complaint electronically, you can email the CAO at CAO@worldbankgroup.org. You can learn more about the CAO and how to file a complaint at http://www.cao-ombudsman.org/