DJERDAP II HPP REHABILITATION - FIRST PHASE (EIB-20230692)

Regions
  • Europe and Central Asia
Geographic location where the impacts of the investment may be experienced.
Countries
  • Serbia
Geographic location where the impacts of the investment may be experienced.
Specific Location
Mihajlovac, Bor District
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • European Investment Bank (EIB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
U
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Borrower
JSC Elektroprivreda Srbije Belgrade
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
  • Hydropower
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 97.81 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 90
Converted using 2024-05-16 exchange rate.
Loan Amount (USD)
$ 97.81 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 90
Converted using 2024-05-16 exchange rate.
Project Cost (USD)
$ 97.81 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 90
Converted using 2024-05-16 exchange rate.
Other Related Projects
Primary Source

Original disclosure @ EIB website

Updated in EWS Jun 28, 2024

Disclosed by Bank May 16, 2024


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

As stated by the EIB, the project consists of an allocation of EPS Green Financing framework loan (2022-0716) to finance the rehabilitation of three hydropower units and related auxiliary and electrical systems by 2030. The powerplant is located inside Iron Gate II dam on the Serbian side of the Danube River.

The operation is an allocation of the framework loan EPS Green Financing (EIB/20220716) which finances promoter's key green investments in the electricity sector for the period 2024-2030 with a view to increase ultimately the national share of renewables to the target set by 2030. The operation fits into the Promoter's "Go Green Strategy 2022-2035" and supports Serbia's green transition by contributing to the modernisation of the existing portfolio of hydro power plants. The Project allocation aims at extending the useful life of three units at Djerdap 2 HPP by up to 30 years and increase their annual electricity generation, installed capacity power from 27 MW up to 32 MW and provide additional flexibility to the Serbian electricity transmission network by allowing more renewable energy sources to be connected.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.
Private Actors Description
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

As stated on the company's website, Joint Stock Company Elektroprivreda Srbije is the largest company in Serbia, representing economic and energy backbone of the country. Main activities of EPS JSC are electricity generation, supply, distribution and trading. 

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Javno Preduzece "Elektroprivreda Srbije" Beograd - EPS Client Energy

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

No project contacts provided at the time of disclosure.

ACCESS TO INFORMATION

You can submit an information request for project information at: https://www.eib.org/en/infocentre/registers/request-form/request-form-default.htm

ACCOUNTABILITY MECHANISM OF EIB

The EIB Complaints Mechanism is designed to facilitate and handle complaints against the EIB by individuals, organizations or corporations affected by EIB activities. When exercising the right to lodge a complaint against the EIB, any member of the public has access to a two-tier procedure, one internal - the Complaints Mechanism Office - and one external - the European Ombudsman. A complaint can be lodged via a written communication addressed to the Secretary General of the EIB, via email to the dedicated email address: complaints@eib.org, by completing the online complaint form available at the following address: http://www.eib.org/complaints/form via fax or delivered directly to the EIB Complaints Mechanism Division, any EIB local representation office or any EIB staff. For further details, check: http://www.eib.org/attachments/strategies/complaints_mechanism_policy_en.pdf

When dissatisfied with a complaint to the EIB Complaints Mechanism, citizens can then turn towards the European Ombudsman. A memorandum of Understanding has been signed between the EIB and the European Ombudsman establishes that citizens (even outside of the EU if the Ombudsman finds their complaint justified) can turn towards the Ombudsman on issues related to 'maladministration' by the EIB. Note that before going to the Ombudsman, an attempt must be made to resolve the case by contacting the EIB. In addition, the complaint must be made within two years of the date when the facts on which your complaint is based became known to you. You can write to the Ombudsman in any of the languages of the European Union. Additional details, including filing requirements and complaint forms, are available at: http://www.ombudsman.europa.eu/atyourservice/interactiveguide.faces

How it works

How it works