As stated by the EBRD, the project involves the development, construction, and operation of a 100 MW wind power plant and a 15 km, 220 kV overhead transmission line in the Bukhara region of Uzbekistan, developed by Voltalia SA. Overhead transmission line will be built as part of the adjacent Artemisya Battery Energy Storage System (BESS) project, developed by Voltalia SA.
INformation on the investment amount was not provided at the time of disclosure.
As stated by Bloomberg, Voltalia operates as an energy producer and service provider company. The Company generates electricity from biomass, solar, and wind resources, as well as provides renewable energy project development services. Voltalia serves residential, commercial, and industrial sectors worldwide.
| Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
|---|---|---|---|---|---|---|
| - | - | - | - | Voltalia SA | Client | Energy |
Client - Voltalia SA:
Zukhra Sharipova - Social Advisor, Voltalia
Email: z.sharipova@voltalia.com
Phone: +998773537318
Address: Shahrisabz street, block 5A 100060, Mirabad District, Tashkent
Website: https://www.artemisya-hybrid.com/en
Full ESIA documentation is available locally at:
EBRD Tashkent Resident Office, Banking Association of Uzbekistan, 13th floor, 1, Qoratosh Street, Tashkent, 100027, Uzbekistan
ACCESS TO INFORMATION
You can request information by emailing: accessinfo@ebrd.com or by using this electronic form: https://www.ebrd.com/eform/information-request
ACCOUNTABILITY MECHANISM OF EBRD
The Project Complaint Mechanism (PCM) is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an European Bank for Reconstruction and Development (EBRD)-financed project. If you submit a complaint to the PCM, it may assess compliance with EBRD's own policies and procedures to prevent harm to the environment or communities or it may assist you in resolving the problem that led to the complaint through a dialogue with those implementing the project. Additionally, the PCM has the authority to recommend a project be suspended in the event that harm is imminent.
You can contact the PCM at: pcm@ebrd.com or you can submit a complaint online using an online form at: http://www.ebrd.com/eform/pcm/complaint_form?language=en
You can learn more about the PCM and how to file a complaint at: http://www.ebrd.com/work-with-us/project-finance/project-complaint-mechanism.html