Nakkas-Basaksehir Motorway Project (DFC-NAKKAS)

Countries
  • Turkiye
Geographic location where the impacts of the investment may be experienced.
Specific Location
Istanbul
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • US International Development Finance Corporation (DFC)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Borrower
Meridiam Eurasia SAS
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Infrastructure
  • Transport
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Guarantee
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 350.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ DFC website

Updated in EWS Apr 13, 2024


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the Bank’s website, the proposed Project involves DFC political risk insurance for up to $350 million for a greenfield motorway project in Istanbul Turkey. The Build-Operate-Transfer Project was awarded to the construction group, Ronesans, in July 2020, under a 20-year concession. The Project consists of a new 4-lane dual toll road with a total length of 30.64 km (including connection roads) and the 1,619 m long Sazlidere Cable Stayed Bridge. The Project is the final section (8th section) of the Northern Marmara Motorway (NMM). The NMM was originally composed of seven sections connecting Asia and Europe with an uninterrupted traffic flow. These seven sections have been completed and are under operation.

The Project is located in the western part of Istanbul Province and passes through 15 settlements in four districts (Basaksehir, Arnavutkoy, Avcilar and Catalca). These are densely populated areas with diverse economic livelihood activities as well as hosting large residential apartment buildings, public service institutions and sports facilities.

In addition, the following auxiliary features are included in the Project:
• Temporary construction components (e.g., two camp sites, quarries and borrow pits, surplus material dump sites);
• Cable Stayed Bridge (1619 m (length) X 46 m (width) and tower height of 196m), two towers, emergency and maintenance walkways on both sides, lighting two energy centers will be built at the base of each pylon of the bridge;
• Toll booths (number has not been specified yet); free flow systems and tollgate toll collection systems will be incorporated;
• Motorway will be fenced with no pedestrian access;
• Coated shoulders with emergency stripes and reserve shoulders;
• Viaducts will be used in 5 locations (Arnaavutkoy District and four locations in Basaksehir District);
• Ten interchanges – generally 2-lanes, typical lane width of 10.5 m, shoulders, crash strips;
• Underpasses (18), overpasses (28), and culverts (55) (to facilitate farm roads, wildlife and people movement, and water courses);
• Mechanically Stabilized Earth (MSE) walls and retaining walls for reinforcement of embankments (approximately 10 km);
• Draining system of ditches, canals, pipes, manholes, and discharge structures to remove surface and subsurface waters to ensure safe traffic flow; and
• Relocation of overhead transmission lines.

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

Project has been reviewed against DFC’s categorical prohibitions and determined to be categorically eligible. The Project is screened as Category A because projects involving extensive rehabilitation and upgrading of a significant length of major highway can have significant adverse and social impacts that are diverse, irreversible or unprecedented. Primary environmental and social issues of concern include:
• Noise and vibration;
• Erosion and sedimentation;
• Impacts to flora and fauna in terrestrial and freshwater habitats;
• Community health and safety, including traffic safety;
• Occupational health and safety of Project workers;
• Cumulative environmental and social impacts;
• Physical and economic displacement from land acquisition; and
• Potential adverse impacts on archeological and built cultural heritage.

People Affected By This Project
People Affected By This Project refers to the communities of people likely to be affected positively or negatively by a project.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

A political risk insurance for up to $350 million for a greenfield motorway project in Istanbul Turkey.

Private Actor Relationship
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

Private Actors Description
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Meridiam Eurasia SAS Client -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Nakkas Otoyol Yatirim ve Isletme A.S. Office:
Cankaya mah. Ataturk Bulvari No: 144-146 Cankaya, Ankara

ACCESS TO INFORMATION

Unlike many other development finance institutions, DFC does not currently have an access to information policy.

Under the United States Freedom of Information Act (FOIA), DFC is obliged to respond to reasonably formulated requests for Agency records. However, DFC may apply exemptions from release to certain types of information and may charge fees in responding to requests. DFC has a designated FOIA officer who is trained in how to respond to requests and implement the law. You can learn more about filing a FOIA request at: https://www.dfc.gov/foia

ACCOUNTABILITY MECHANISM OF THE UNITED STATES INTERNATIONAL DEVELOPMENT FINANCE CORPORATION (DFC)

The Office of Accountability is an independent office that addresses complaints about environmental or social issues related to DFC-supported projects. The office provides communities an opportunity to have concerns independently reviewed and addressed. If you submit a complaint to the Office of Accountability, it may assist you by either seeking to address your problems by facilitating a problem solving dialogue between you and those implementing the project and/or investigating whether the DFC complied with its policies to prevent environmental, social, human rights, and labor harms.

You can find more information about the Office of Accountability at: https://www.dfc.gov/who-we-are/office-accountability