According to the AIIB, the project development objective is to meet Jordan's critical electricity peak demand growth and strengthen grid stability and reliability for increased renewable energy integration by developing a combined-cycle gas-fired power plant as dispatchable generation capacity.
The Project involves financing the development, construction, operation of a greenfield combined-cycle gas-turbine (CCGT) power plant of 700MW capacity and associated infrastructure in Mafraq, Jordan. The Project is sponsored by Etihad Development Company (EDC) and will be implemented through a dedicated project company, Sharikat Al Khanasri Lil Taqa PSC.
The Project is supported by a 25-year Power Purchase Agreement (PPA) signed between the Project Company and the National Electric Power Company (NEPCO) of Jordan.
The Project forms part of NEPCO's Electricity Master Plan 2025-2035 and will serve as a dispatchable generation to cover Jordan's rising peak loads and to address the structural mismatch between its load profile and renewable generation. Moreover, as a synchronous generation, the plant will provide inertia and voltage support to maintain grid stability, thereby supporting Jordan's target to increase the share of variable renewable energy in the power generation mix. The Project will also contribute to lowering the carbon intensity of Jordan's power system by displacing older and more emission-intensive fossil fuel generation.
As stated by the Boycott UAE Campaign, Etihad Water and Electricity, commonly known as EtihadWE, is a UAE state-owned utility responsible for supplying electricity and desalinated water across several Northern Emirates.
| Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
|---|---|---|---|---|---|---|
| National Electric Power Company (NEPCO) | Buyer | Energy | contracts with | Etihad Water and Electricity (EtihadWE) | Client | Infrastructure |
AIIB Team Leaders:
Hoon Lee - Investment Officer
Email: hoon.lee@aiib.org
Apurv Gupta - Investment Officer
Email: apurv.gupta@aiib.org
Client - Sharikat Al Khanasri Lil Taqa PSC (Etihad Development Company):
Mohamed El Banna - Head of BD & Investments
Email: Mohamed.Elbanna@etihadwe.ae
ACCESS TO INFORMATION
You can submit an information request for project information at: https://www.aiib.org/en/contact/information-request/index.html
ACCOUNTABILITY MECHANISM OF AIIB
The AIIB has established the Accountability Mechanism for Project-Affected People (PPM). The PPM provides Òan opportunity for an independent and impartial review of submissions from Project-affected people who believe they have been or are likely to be adversely affected by AIIBÕs failure to implement the ESP in situations when their concerns cannot be addressed satisfactorily through Project level GRMs or AIIB Management processes.Ó Two or more project-affected people can file a complaint. Under the current AIIB policy, when the bank co-finances a project with another development bank, it may apply the other bank's standards. You can refer to the Project Summary Information document to find out which standards apply. You can learn more about the PPM and how to file a complaint at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/how-we-assist-you/index.html
The complaint submission form can be accessed in Arabic, Bahasa Indonesia, Bengali, Chinese, English, Tagalog, Hindi, Nepali, Russian, Turkish, or Urdu. The submission form can be found at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/submission/index.html