According to the AIIB, the objective of the project is to support Turkiye energy transition through the expansion of solar photovoltaic installed capacity.
The Project comprises the development, construction, and operation of a solar photovoltaic (PV) plant with 100 MW of installed capacity (134MWp) in the municipality of Erzin, in the province of Hatay. The Sponsor of the Project is IC Ictas Group, a Turkish conglomerate founded in 1969. The Group owns and operates 1,450 MW of installed capacity, mainly thermal and hydropower plants, and distributes approx. 6.57 billion kWh per annum of electricity.
The Project was awarded to IC Ictas Enerji in June 2022 through the YEKA GES-4 reverse auction under a license period of 30 years. The auction allocated 700 MW of capacity across 12 solar PV projects under a ceiling price of up to TRYkr 95/kWh. The Project secured an inflation and foreign exchange (FX)-linked tariff of TRYkr 58.4/kWh whereas tariff bids ranged between TRYkr 49-59.7 /kWh. The Project is entitled to sell up to 23 GWh per MW of capacity installed at the Tariff. The Project agreements were signed between IC Ictas Enerji and the Ministry of Energy and Natural Resources (MENR) in August 2022.
As stated by the AIIB, the proposed loan of up to USD32.5 million is part of a financing package of USD65million to be provided by AIIB and Turkiye Sinai Kalkinma Bankasi A.S. (TSKB).
As stated by Bloomberg, IC Ictas Insaat Sanayi Ve Ticaret A.S. provides construction services. The Company produces airports, power plants, infrastructures, superstructure facilities, and civil structure projects. IC Ictas Insaat Sanayi Ve Ticaret also offers services in global air and sea port management, energy, tourism, industrial facilities and international activities.
Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
---|---|---|---|---|---|---|
- | - | - | - | Turkiye Sinai Kalkinma Bankasi A.S. (TSKB) | Investor | Finance |
IC ICTAS | Parent Company | Construction | owns | IC Ictas Enerji Yatirim Holding | Client | Energy |
AIIB Team Leader:
Daniel Pérez Pedraza - Investment Associate
Email: daniel.pedraza@aiib.org
Borrower - IC Ictas Gunes Enerji Uretim ve Ticaret A.S.:
Elif Gumrukcuoglu - Project Finance Director
Email: elif.gumrukcuoglu@ic.com.tr
Parent Company - IC Ictas Insaat Sanayi ve Ticaret A.S. (IC Ictas Group):
Basak Basari - Project Finance Senior Manager
Email: basak.basari@ic.com.tr
ACCESS TO INFORMATION
You can submit an information request for project information at: https://www.aiib.org/en/contact/information-request/index.html
ACCOUNTABILITY MECHANISM OF AIIB
The AIIB has established the Accountability Mechanism for Project-Affected People (PPM). The PPM provides Òan opportunity for an independent and impartial review of submissions from Project-affected people who believe they have been or are likely to be adversely affected by AIIBÕs failure to implement the ESP in situations when their concerns cannot be addressed satisfactorily through Project level GRMs or AIIB Management processes.Ó Two or more project-affected people can file a complaint. Under the current AIIB policy, when the bank co-finances a project with another development bank, it may apply the other bank's standards. You can refer to the Project Summary Information document to find out which standards apply. You can learn more about the PPM and how to file a complaint at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/how-we-assist-you/index.html
The complaint submission form can be accessed in Arabic, Bahasa Indonesia, Bengali, Chinese, English, Tagalog, Hindi, Nepali, Russian, Turkish, or Urdu. The submission form can be found at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/submission/index.html