Gabon - Kinguele Aval Hydropower Project (AFDB-P-GA-F00-008)

Countries
  • Gabon
Geographic location where the impacts of the investment may be experienced.
Specific Location
Mbei River
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • African Development Bank (AFDB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Approved
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
U
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jun 30, 2021
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Asonha Energie S.A.
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 23.20 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 20
Converted using 2022-04-04 exchange rate.
Project Cost (USD)
$ 196.34 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 178.5
Converted using 2022-04-04 exchange rate.
Primary Source

Original disclosure @ AFDB website

Updated in EWS Jun 28, 2022


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the bank website, the project entails the design, construction, and operation of Kinguélé Aval hydropower plant, with an estimated installed capacity of 34.1 MW and net annual gross output of 203 GWh. The project will be located c. 90 km from Libreville on the Mbei River, located next to the Monts de Cristal (Estuaire region, North - West of Gabon). Two hydro dams, built upstream in the Mbei Valley, are regulating the river namely Kinguélé Amount (57.6 MW), 10km upstream and Tchimbélé (68MW), 50km upstream. All electricity generated by the Project is expected to be sold to the Government of Gabon (“GoG”) on a Take or Pay basis.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

U.A 16,060,516.02

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - Gabon Power Company Parent Company -
- - - - Meridiam SAS Parent Company -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

CONTACT INFORMATION

private-sector@afdb.org

ACCESS TO INFORMATION

You can submit an information request for project information at: https://www.afdb.org/en/disclosure-and-access-to-information/request-for-documents. Under the AfDBÕs Disclosure and Access to Information policy, if you feel the Bank has omitted to publish information or your request for information is unreasonably denied, you can file an appeal at https://www.afdb.org/en/disclosure-and-access-to-information/appeals-process.

ACCOUNTABILITY MECHANISM OF AfDB

The Independent Review Mechanism (IRM), which is administered by the Compliance Review and Mediation Unit (CRMU), is the independent complaint mechanism and fact-finding body for people who have been or are likely to be adversely affected by an African Development Bank (AfDB)-financed project. If you submit a complaint to the IRM, it may assist you by either seeking to address your problems by facilitating a dispute resolution dialogue between you and those implementing the project and/or investigating whether the AfDB complied with its policies to prevent environmental and social harms. You can submit a complaint electronically by emailing crmuinfo@afdb.org, b.kargougou@afdb.org, b.fall@afdb.org, and/or s.toure@afdb.org. You can learn more about the IRM and how to file a complaint at: https://www.afdb.org/en/independent-review-mechanism/

How it works

How it works