Urban Water Supply and Sanitation Sector Project - Second Additional Financing (ADB-51271-004)

Countries
  • Solomon Islands
Geographic location where the impacts of the investment may be experienced.
Specific Location
Auki, GHA, Gizo, Munda, Noro, and Tulagi
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • Asian Development Bank (ADB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
C
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Borrower
Government of Solomon Islands - Ministry of Finance and Treasury
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Grant
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 25.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Bank Documents
Primary Source

Original disclosure @ ADB website

Updated in EWS May 13, 2024

Disclosed by Bank Mar 22, 2024


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the Bank’s website, in September 2019, the Asian Development Bank (ADB) approved the Urban Water Supply and Sanitation Sector Project (the ongoing project), which adopts a sector approach for developing sustainable, inclusive, and climate resilient water supply and improved sanitation in the greater Honiara area (GHA) and in five other towns of Auki, Gizo, Munda, Noro, and Tulagi in Solomon Islands. The ADB financing comprises a (i) concessional loan of $28.00 million from ADB's ordinary capital resources, and (ii) a grant not exceeding $9.00 million from ADB's Special Fund resources (Asian Development Fund). The ongoing project is cofinanced through a European Union (EU) grant of 18.00 million ($20.35 million equivalent), administered by ADB; a World Bank concessional loan of $15.00 million.

The ADB and World Bank financing were declared effective in April 2020. In September 2021, ADB approved an additional financing grant of $4.59 million, sourced from Global Environment Facility (GEF) and administered by ADB. In December 2023, a second additional financing of $15.00 million from World Bank was approved. The ongoing project closing date is 31 December 2028. The executing agency is the Ministry of Finance and Treasury and the implementing agency is the Solomon Islands Water Authority (SIWA). The ongoing project outputs include: (i) continuous, safe, and climate resilient urban water supply ensured; (ii) urban sanitation services are effective, efficient, and safe in GHA; (iii) enhanced and sustained awareness and behaviors of hygiene and water conservation in GHA and five towns; (iv) SIWA is financially and technically sustainable; and (v) management of Honiara's drinking water source area strengthened to build resilience to climate change.

Performance of the Ongoing Project. Progress towards achieving the ongoing project outcome, following the outcome level indicators, is summarized below:

Water supply coverage: Strong progress has been made towards achieving the water supply coverage target of 16,500 households, with 16,186 households connected at the end of August 2023.

Nonrevenue water (NRW) reduction: Progress towards reducing NRW in Honiara to 30% by 2027 is off track. Average monthly NRW has marginally decreased from the 2019 baseline value of 62% to 61% in August 2023.

Sewerage coverage: Increasing SIWA's sewerage coverage to 4,000 households is off track as the project's Honiara sewer expansion subproject has yet to go to market for bidding. As of August 2023, only 661 households were connected to SIWA's sewerage networks.

On-site sanitation management: Progress towards achieving the target of 14,000 households in greater Honiara benefiting from improved onsite sanitation policies is on track following preparation of the draft GHA Comprehensive Sanitation Plan 20222026.

Water quality in Honiara: The water quality compliance target for sewage discharged from the Honiara sewer systems is likely to be partially achieved if works to reconfigure the sewer system proceed under the additional financing.

SIWA financial sustainability: Full recovery of annual operation and maintenance costs, asset depreciation costs, debt servicing costs from user charges and government community service obligation payments is essential for SIWA's financial sustainability. SIWA achieved full cost recovery in 2020 and fell short of the target (by less than 3%) in 2021 and 2022.

Additional Financing Rationale: The project is facing major cost overruns because the price of goods and civil works have increased substantially since its approval in 2019. This escalation has been seen in most of ADB's Pacific developing member countries; recent bids for civil works in Solomon Islands indicate that construction costs have increased by up to 70% since March 2020. Status on each performance indicator is outlined below.

(i)The project is delivering expected outputs despite implementation delays caused by the coronavirus disease pandemic, which slowed design work, impacted market availability of goods and services, increased market prices, and limited ability of consultants and contractors to mobilize to Solomon Islands. The ongoing project has made considerable progress and is expected to deliver project outcomes and outputs by the completion date.

(ii)Project implementation progress is satisfactory. On 30 September 2023, overall progress was estimated at 35.3% against an overall elapsed project duration of 47.8%. To date, 39 contracts with an aggregate cost of $63.2 million equivalent (69%) had been awarded, of which $53.9 million is funded by ADB, GEF, and World Bank, and $9.3 million by SIWA. Disbursements from ADB and ADB-administered loan and grant accounts amounted to $21.3 million (34%); and disbursements from the World Bank loan account amounted to $2.8 million (19%).

(iii)The government is complying with loan and grant covenants and assurances, including those concerning anticorruption measures, gender, procurement, consulting services, disbursement and, safeguard policies. No safeguards compliance issues have arisen.

(iv)Project risks identified are being managed and mitigated.

(v)ADB's project performance rating has declined to "for attention" due to the delayed submission of fiscal year (FY) 2022 annual entity financial statements (AEFS). The FY2022 AEFS is currently being reviewed by the Solomon Islands Office of the Auditor General (OAG), and when approved will be submitted to ADB and the World Bank.

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

Environment: C

Involuntary Resettlement: C

Indigenous Peoples: C

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Asian Development Fund: US$ 25.00 million


Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

No contacts available at the time of disclosure.

ACCESS TO INFORMATION

You can submit an information request for project information at: https://www.adb.org/forms/request-information-form

ADB has a two-stage appeals process for requesters who believe that ADB has denied their request for information in violation of its Access to Information Policy. You can learn more about filing an appeal at: https://www.adb.org/site/disclosure/appeals

ACCOUNTABILITY MECHANISM OF ADB

The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main.

How it works

How it works