Contribute Information
Can you contribute information about this project?
Contact the EWS Team
According to the Bank’s website, the investment program will improve the accessibility of the road network in Sri Lanka's rural areas and thereby increase the involvement of the rural population in nationwide economic and social development. It will upgrade and maintain about 3,000 kilometers (km) of rural access roads to an all-weather standard; rehabilitate and maintain to a good condition about 400km of national roads in Eastern, Northern, Uva, and Western provinces; and improve the capacity of road agencies with respect to safeguards, road safety, maintenance, research capacity, and road design and construction. Tranche 1 will finance the first slice of the projects.
Given the various external challenges experienced during the MFF implementation, including the COVID-19 pandemic and the 2022 economic crisis, which delayed program implementation and necessitated a reduction in the originally-envisaged amount of the tranche 5 loan, it is proposed to accordingly change the scope of the MFF by recalibrating the balance of activities for rural and national roads. To ensure that the scope of tranche 5 is sufficiently realistic to achieve a well-ordered completion of the MFF within its availability period, targets for construction and upgrading of overall roads under the MFF, and associated road maintenance targets, will be revised. It is proposed to change the target for rural access roads: (i) the target for rural access roads from 3,400 km to 2,958 km; (ii) the target for national roads from 340 km to 397 km ; and (iii) consequential revision of maintenance work indicators.
All roads identified under the program have limited footprints. The program includes no significant capacity improvement, involving mainly rehabilitation and maintenance of existing rural and national roads located outside critical habitat or protected areas and their buffer zones. Environmental impacts include typical road construction-related issues such as generation of dust and other air pollutants, noise, solid and liquid waste from construction sites and workers' camps, and community and occupational health and safety concerns. In line with the requirements of ADB SPS (2009), a review of the revised project scope was conducted through an Environmental Diligence Report to determine whether it would result to additional environmental impacts. There have been no substantial changes to the original project scope that would alter its environmental classification, anticipated impacts or require additional assessments. The review confirmed that the scope remains consistent with the previous tranches environmental classification (Category B) and no updates to the existing IEEs or EMPs were required.
All roads under the program have been assessed for involuntary resettlement and only those that do not require expropriation have been selected for financing under the program. Road improvement works are presently carried out in Uva, Eastern, Northern and Western provinces. The work is carried out within the available road corridors except at certain locations where small strips of and from adjacent land lots have been required to improve the road user safety and to develop lead-away drains. No voluntary land donation has taken place for national roads since works were taken up only where ROW is sufficient.
No indigenous peoples communities as defined by ADB's Safeguard Policy Statement have been identified in the subproject areas.
The financing amount is $90,000,000, which will be financed on a loan basis by ADB’s ordinary capital resources.
Counterpart: $12,400,000
Project Cost: $102,400,000
Chairman - Ministry Procurement Committee
Ministry of Highways
“Maganeguma Mahamedura”
No. 216, Denzil Kobbekaduwa Mawatha
Koswatta
Battaramulla, Sri Lanka
ACCESS TO INFORMATION
You can submit an information request for project information at: https://www.adb.org/forms/request-information-form
ADB has a two-stage appeals process for requesters who believe that ADB has denied their request for information in violation of its Access to Information Policy. You can learn more about filing an appeal at: https://www.adb.org/site/disclosure/appeals
ACCOUNTABILITY MECHANISM OF ADB
The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main.