Southeast Gobi Urban and Border Town Development Project --Additional Financing (ADB-42184-024)

Countries
  • Mongolia
Geographic location where the impacts of the investment may be experienced.
Specific Location
Avairkheer, Tsetserleg
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • Asian Development Bank (ADB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Active
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
B
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Apr 22, 2016
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Government of Mongolia
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Technical Cooperation
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 19.43 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 20.43 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ ADB website

Updated in EWS Jul 2, 2020

Disclosed by Bank Mar 31, 2016


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

The additional financing and the administration of the TA grant will scale up and extend the socioeconomic benefits of the project by improving the quality and reliability of wastewater management services in two aimag centers from the current project, and by extending service improvements to two additional prominent and fast-growing aimag centers. The additional financing will also continue to strengthen through the TA, the wastewater management capabilities of aimag public utility service organizations (PUSOs) in both the current and additional project aimag centers.

 

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Bill and Melinda Gates Foundation US$ 1.00 million


Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Ministry of Construction and Urban Development
Ulaanbaatar 211238
Barilgachdyn Talbai 3 Mongolia

ACCOUNTABILITY MECHANISM OF ADB

The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main

How it works

How it works