Timor Solar (IFC-48399)

Countries
  • Timor-Leste
Geographic location where the impacts of the investment may be experienced.
Specific Location
Approximately 14 km east of Manatuto, directly adjacent to the main road from Manatuto to Baucau.
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • International Finance Corporation (IFC)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
B
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jan 27, 2026
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Manatuto Renewables Power S.A.
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
The service or industry focus of the investment. A project can have several sectors.
Loan Amount (USD)
$ 19.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 106.20 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ IFC website

Updated in EWS Mar 16, 2026

Disclosed by Bank Jan 26, 2026


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the bank's website, the "proposed IFC investment is a senior loan with a total package of up to US$ 85 million that will support the Laleia Solar Independent Power Producer (IPP) Project (the “Project”), a utility-scale solar photovoltaic (PV) plant with a Battery Energy Storage System (BESS). The project, a 90MWp/72MWac PV power plant with an 80 MWh BESS, is located in the Laleia area of Timor-Leste and is being developed by a consortium comprising EDF Power Solutions (EDFps; formerly EDF Renewables, a subsidiary of EDF Group) and I-Environment Investments Pacific Pty Ltd (a subsidiary of Itochu), who jointly are the project sponsors. The Project was publicly tendered by the Electricidade de Timor-Leste (EDTL, offtaker), the state-owner utility and in November 2024 the consortium won the bid to develop the project. The Project will benefit from a 25-year power purchase agreement with EDTL. A Special Purpose Vehicle (“SPV”) is being established by the consortium in Timor Leste to implement and operate this Project.The Project consists of the construction, operation, and maintenance of the solar PV plant and BESS. The construction including detailed engineering is anticipated to take about 24 months, with operations expected to begin by around March 2028.The Laleia Solar IPP consists of ground-mounted PV modules covering less than 100 hectares within a larger allocated project area of 350 hectares (the layout to be confirmed during detailed engineering). Supporting infrastructure includes inverter stations connected by underground cables, a new on-site substation to step up voltage for grid integration, and a direct connection to the existing national 150 kV transmission line along the site’s southern boundary via an overhead transmission line of approximately 0.3 kilometers. Additional facilities include secure perimeter fencing, access and internal roads, and ancillary buildings for operations and maintenance. The project will be designed, procured and constructed by China Manufacturing Engineering Corporation group (CMEC group; EPC contractor) on a turnkey basis. The scope of CMEC group work will also include a two-year period of operations and maintenance (O&M), during which CMEC will be responsible for the entire plant, namely both the PV plant and the BESS. From the third year onwards, the plan is to bring PV and BoP O&M activities in-house. For the BESS, a long-term service agreement will be established with a selected contractor to ensure ongoing support and maintenance.The project site is located on Timor-Leste’s north coast, about 70 kilometers east of Dili, within the Laleia Administrative Post of Manatuto Municipality. The project will be constructed on land selected and acquired by Electricidade de Timor-Leste. The site is directly adjacent to a national main road (Manatuto–Baucau highway), providing easy access for construction and operation. No additional roads are needed for site entry. The project site spans approximately 350 hectares in a broad, low-lying valley between the main coastal road and the shoreline. The site forms the lower part of a watershed that drains steep uplands into a flat coastal floodplain. The area is primarily used for communal grazing and features tamarind trees and mixed scrubland/grassland vegetation. The site is not intensively cultivated and is situated several kilometers from the nearest village".

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

EDF Power Solutions S.A.
Adrien Hellio
Project Manager
+33 (0)7 77 93 91 91
adrien.hellio@edf-power.com
43 Boulevard des Bouvets,CS 90310, 92741 Nanterre Cedex
https://edf-powersolutions.com/en/ 


ACCESS TO INFORMATION

You can submit a request for information disclosure at: https://disclosures.ifc.org/#/inquiries

If you believe that your request for information from IFC has been unreasonably denied, or that this Policy has been interpreted incorrectly, you can submit a complaint at the link above to IFC's Access to Information Policy Advisor, who reports directly to IFC's Executive Vice President.

ACCOUNTABILITY MECHANISM OF IFC/MIGA

The Compliance Advisor Ombudsman (CAO) is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an IFC or MIGA- financed project. If you submit a complaint to the CAO, they may assist you in resolving a dispute with the company and/or investigate to assess whether the IFC is following its own policies and procedures for preventing harm to people or the environment. If you want to submit a complaint electronically, you can email the CAO at CAO@worldbankgroup.org You can learn more about the CAO and how to file a complaint at http://www.cao-ombudsman.org

How it works

How it works