The Project constructs a 57.1 km expressway between Ben Luc and Long Thanh in the south of Ho Chi Minh City (HCMC), which is a short link of the Greater Mekong Subregion (GMS) Southern Economic Corridor.
The project expressway is divided into a western section (21.14 km), a middle section (10.71 km), and an eastern section (25.25 km). For the expressway construction, ADB finances the western and eastern sections, and Japan International Cooperation Agency (JICA) finances the middle section. The project was estimated to cost $1.608 billion at appraisal, inclusive of local taxes, contingencies, and financing charges during development. Tranche 2 in the amount of $286 million will cover construction of the eastern section of the expressway.
Total (Amount in US$ million)
ADB 286.00
Counterpart 48.30
JICA 305.52
Project Cost 639.82
Vietnam Expressway Corporation
Hamlet 2, Linh Nam Ward
Hoang Mai District, Hanoi
ACCOUNTABILITY MECHANISM OF ADB
The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main