Hunan Flood Management Sector Project (ADB-37641-013)

Countries
  • China
Geographic location where the impacts of the investment may be experienced.
Specific Location
Hunan
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • Asian Development Bank (ADB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Canceled
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
A
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Jun 29, 2006
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
Government of People's Republic of China
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Agriculture and Forestry
  • Water and Sanitation
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 200.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 497.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ ADB website

Updated in EWS Jul 2, 2020

Disclosed by Bank Mar 30, 2016


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

The project supported the People's Republic of China's (PRC) and the Hunan Provincial Government's (HnPG) policies and plans for flood protection investments. Since 2000, the Ministry of Water Resources had been changing its policy and strategy from a flood-control approach to a river basin-based integrated flood management approach. The policy shift was economically and environmentally sustainable and aimed to be socially inclusive. The project supported the implementation of an area and time slice of Hunan's integrated flood-control program under the Hunan Provincial 11th and 12th Five-Year Planx (2006-2010, 2011-2015), focusing on a comprehensive framework for flood control, management, and forecasting in the four mountainous river basins-Lishui, Xiangjiang, Yuanjiang, and Zishui. Flood protection works was constructed for up to 35 subprojects. Nonstructural measures were developed to strengthen hydrological monitoring, improve flood forecasting, and enhance flood warning systems. An advisory technical assistance (TA) was provided to support sustainable flood management by assisting the Provincial Water Resources Department (PWRD) to plan and assess nonstructural aspects of flood management and strengthen capacity in plan implementation.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Spanish Cooperation Fund for Technical Assistance US$ 500,000
Multi-Donor Trust Fund under the Water Financing Partnership Facility US$ 60,000.


Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Hunan Provincial Government
LIKUANGYUN@TSINGHUA.ORG.CN
418 North Shaoshan Road
Shangsha City, Hunan Province
People's Republic of China

ACCOUNTABILITY MECHANISM OF ADB

The Accountability Mechanism is an independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an Asian Development Bank-financed project. If you submit a complaint to the Accountability Mechanism, they may investigate to assess whether the Asian Development Bank is following its own policies and procedures for preventing harm to people or the environment. You can learn more about the Accountability Mechanism and how to file a complaint at: http://www.adb.org/site/accountability-mechanism/main

How it works

How it works