REDSTONE (IFC-34050)

Countries
  • South Africa
Geographic location where the impacts of the investment may be experienced.
Financial Institutions
  • International Finance Corporation (IFC)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
B
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Voting Date
Sep 1, 2016
Date when project documentation and funding is reviewed by the Board for consideration and approval. Some development banks will state a "board date" or "decision date." When funding approval is obtained, the legal documents are accepted and signed, the implementation phase begins.
Borrower
REDSTONE CSP
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Energy
The service or industry focus of the investment. A project can have several sectors.
Potential Rights Impacts
  • Cultural Rights
  • Healthy Environment
  • Labor & Livelihood
  • Right to Water
Only for projects receiving a detailed analysis, a broad category of human and environmental rights and frequently at-risk populations.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 72.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Project Cost (USD)
$ 833.00 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Primary Source

Original disclosure @ IFC website

Updated in EWS Feb 26, 2019

Disclosed by Bank Dec 31, 2015


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

Project Summary: “The Project involves the design, construction, ownership, operation and maintenance of a new 100 MW (net) molten salt tower base Concentrated Solar Power (CSP) plant. The Project is to sell power to Eskom under a 20 year (post construction) PPA. The Project will be structured as a special purpose vehicle and the Project Company is ACWA Power Solar Reserve Redstone Solar Thermal Power Plant Proprietary Limited. Construction is due to commence in August 2015. There are currently two other PV projects on the same farm, the Lesedi and the Jasper PV Power projects.

Location: Northern Cape Province, South Africa – in the Kalahari Mountain Bushveld savannah biome

Resources needed: Remainder of the Farm 469, District Hay, 30 km from Postmasburg in the Northern Cape Province, South Africa. Large volumes of water via the Vaal Gamagara Water Supply Scheme for the construction of the CSP Plant – approximately 117,500m3 per annum during the 29 month construction period.

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

Risk Assessment: Category B. This is a Category B project according to IFC’s Policy and Performance Standards on Environmental and Social Sustainability, because a limited number of specific environmental and social impacts which may result from the project’s construction and operation can be avoided or mitigated by adhering to generally recognized performance standards, guidelines or design criteria.
Project type: Solar, renewable energy generation

APPLICABLE SOCIAL & ENVIRONMENTAL STANDARDS
Based on IFC documents, the following environmental and social safeguard policies are triggered:

PS 1: Assessment and Management of Environmental and Social Risks and Impacts-

PS 2: Labor and Working Conditions- triggered because “construction activities associated with the project will generate short-term direct employment for up to approximately 1400 people (at peak) during the projected 29 month construction period.” The CSP plant’s operations are expected to employ approximately 73 people as full time staff on a permanent basis. Additional persons will be employed as subcontractors. With this comes a need for Human Resources and Occupational Health and Safety.

PS 3: Resource Efficiency and Pollution Prevention - triggered because “The construction and operation of the Concentrated Solar Power may disrupt local hydrological functioning. The likelihood that a loss of infiltration capacity on site generates excess surface flow requires that mitigation measures be put in place during construction and operation of the CSP.” “A significant and diverse waste stream is expected to be generated during the construction phase. Waste streams will include: Construction & Demolition waste, Recyclables, Hazardous waste, and Domestic solid waste. “The noise from the cooling fans will be the loudest and will predominate at areas outside the CSP Plant property. For daytime operations, measurements demonstrated that noise sensitive sites within 2150 meters from the Plant could be significantly impacted by the noise from the Plant….only one site is affected, namely the residence on Farm Humansrus to the north of the development site.”

PS 4: Community Health, Safety and Security- triggered because adequate mitigation measures are required to deal with the adverse impacts during both construction and operation phases, particularly with regard to: i) surface water resources; ii) fair, safe and healthy working conditions for both construction and operational work force, which includes worker accommodation camps erected during construction phases; iii) hazardous and solid waste management; iv) impacts of construction and operation on the natural fauna and flora of the project area and human populations surrounding the project area. There will also be a plan to avoid veld fires.

PS 6 – Biodiversity Conservation and Sustainable Management of Living Natural Resources- triggered because “associated power lines may result in electrocution and collision impacts on avifauna, while the development of various infrastructures will also cause habitat destruction and disturbance. “Collision with the heliostats (mirrors) or the tower is likely to impact on birds” “likely that the occasional bird will collide with the tower or be affected by the bright light of the mirrors. Scorching of birds may also be a risk, particularly fast flying species such as doves, swifts, martins and swallows. Collision of large terrestrial birds with overhead power lines is also likely to occur and is anticipated to be the most significant threat posed by associated infrastructure.” Other aspects that will be affected include migration patterns and suitable habitat for breeding and foraging purposes. The loss of an area as large, as this property, will affect the migration pattern of a number of species that are present in the immediate region. While larger animals are able to avoid unsuitable habitat, smaller animals might not be able to cross or avoid these areas”.

PS 8 – Cultural Heritage - triggered because the Heritage Scoping Report, that forms part of the Heritage Impact Assessment (HIA), has shown that the area between Postmasburg and Daniëlskuil, generally referred to as the Ghaap plateau, has a rich history of occupation from the Stone Age with hunter gatherers to the Thlaping and Thlaro during the Iron Age period. “Field work identified a total of 25 heritage sites which were assessed with 14 sites requiring further mitigation. Cemeteries will be excluded from the development layout and fenced with a 15 meter buffer, as per the South African Heritage Resources Agency (SAHRA) consent letter, and the ESIA. In the event that the cemeteries cannot be excluded from the development, the project documents provide that the graves will be relocated after a full grave relocation process that includes comprehensive social consultation.

People Affected By This Project
People Affected By This Project refers to the communities of people likely to be affected positively or negatively by a project.

OUR RISK ASSESSMENT
Based on the IFC’s project documents, this project poses potential risks to the following human rights:

The Right to a Healthy Environment
There will be a diverse amount of waste water generated from the tower, primarily much chemical pollution. There is a degree of noise pollution from the active base, which affects a nearby residence. The tower lines also pose an obstacle to large terrestrial birds and other terrestrial species. There will be an impact on the migration of animals in the area. The construction and operation of the CSP may disrupt local hydrological functioning. There is the likelihood that a loss of infiltration capacity on site will generate excess surface flow.

Right to Water
Significant volumes of water that are available on site via the Vaal Gamagara Water Supply Scheme for the construction of the CSP Plant – approximately 117,500m3 per annum during the 29 month construction period, may affect the general water supply in the area. There is also the possibility of the waste streams resulting in a good degree of water pollution generated from the project.

Right to Culture
The project document provides that the cemeteries will be closed off and not form part of the project area. Cultural rights will be affected in the event that it becomes necessary to include that portion of the land in the project if the proper customary processes and consultations are not followed in the relocation of the graves. In addition, it is stated that the field work identified a total of 25 heritage sites which were assessed with 14 sites requiring further mitigation.

Labor rights
Project documents state in the contractor’s agreements that the project will generate short-term direct employment for up to approximately 1400 people (at peak) during the projected 29 month construction period, with a minimum of 15% of the workforce must be drawn from local communities and a minimum of 75% from South Africa. The project documents provide for various steps and mechanisms that will be put in place to deal with the large labor force that will be needed for the project. There may be a need for close monitoring of the process especially in relation to basic working conditions and the proposed policies on employee basic services (minimum space, water supply, adequate sewage and garbage disposal system, appropriate protection against heat, cold, damp, noise, fire and disease carrying animals, storage facilities and natural and artificial lighting, and basic medical services). Given the large number of employees required, one must monitor that there is no exploitation of labor forces from communities or nearby countries who may not insist of the standard basic working conditions.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Bank financing: International Finance Corporation
Borrower/Client: Redstone CSP. The Project’s Sponsors are ACWA Power and SolarReserve. ACWA Power is registered and headquartered in the Kingdom of Saudi Arabia. SolarReserve is a Delaware, United States, limited liability company. The shareholders are ACWA Power 50%, the Government Employees Pension Fund which is managed by the Public Investment Corporation 13.5%, Solar Reserve 10%, Old Mutual Life Assurance Company of South Africa (10%), Humansrus Community Trust SPV 6.5% and Pele Green Energy 10%. The US Overseas Private Investment Corporation, the U.S. government’s development finance institution, is also a co-financier.
Amount of bank loan or investment: ZAR864 million (circa US$72 million)
Total project cost: Estimated ZAR10 Billion (US$833 million)

Private Actors Description
A Private Actor is a non-governmental body or entity that is the borrower or client of a development project, which can include corporations, private equity and banks. This describes the private actors and their roles in relation to the project, when private actor information is disclosed or has been further researched.

The Project involves the design, construction, ownership, operation and maintenance of a new 100 MW (net) molten salt tower base Concentrated Solar Power (CSP) plant. The Project is to sell power to Eskom under a 20 year (post construction) PPA. The Project will be structured as a special purpose vehicle and the Project Company is ACWA Power SolarReserve Redstone Solar Thermal Power Plant Proprietary Limited.

Private Actor 1 Private Actor 1 Role Private Actor 1 Sector Relation Private Actor 2 Private Actor 2 Role Private Actor 2 Sector
- - - - REDSTONE CSP Client -

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

Prabashen Govender, Project Director
7th Floor, 90 Grayston Drive, Sandton
South Africa
Phone: +27 11 722 4100
Fax: +27 11 722 4113

ACWA Power
7th Floor, 90 Grayston Drive, Sandton, South Africa

CONSULTATIONS
The ESIA was conducted within the context of the broader South African environmental legislative framework and in line with the National Environmental Management Act (NEMA) Environmental Impact Assessment (EIA) Regulations. This process has a two phase disclosure and consultation process – the first step consisting of the registration of all Interested and Affected Parties (IAPs) followed by a consultation process to identify the potential impacts of the proposed project, and a second step (once the Scoping Report has been approved by DEA) to compile a draft ESIA with specialist reports, and a continuation of the extensive Public Participation Process initiated during the Scoping Phase. During the ESIA comments and issues raised by key stakeholders, identified during the ESIA Scoping Phase, were addressed and feedback was given. The majority of the concerns and comments received during the consultation process related to community benefit and job creation aspects of the project. Stakeholders were kept informed of the ESIA process via public meetings, notices, pamphlets, newspaper advertisements and emails. All registered IAPs were requested to give inputs on each draft report.

The Draft ESIA Report was available for public review at five localities in close proximity to the study area, which were identified as readily accessible to stakeholders and allowed for review and no objections or opposition has been received. There is ongoing communication with stakeholders over the period of the project. In the event that the cemeteries cannot be excluded from the development, the graves will be relocated after a full grave relocation process that includes comprehensive social consultation.

ACCOUNTABILITY MECHANISM OF IFC

The Compliance Advisor Ombudsman (CAO) is the independent complaint mechanism and fact-finding body for people who believe they are likely to be, or have been, adversely affected by an IFC or MIGA- financed project. If you submit a complaint to the CAO, they may assist you in resolving a dispute with the company and/or investigate to assess whether the IFC is following its own policies and procedures for preventing harm to people or the environment. If you want to submit a complaint electronically, you can email the CAO at CAO@worldbankgroup.org. You can learn more about the CAO and how to file a complaint at http://www.cao-ombudsman.org/

How it works

How it works