COSTA RICA ELECTRIC TRAIN (EIB-20230892)

Regions
  • Latin America and Caribbean
Geographic location where the impacts of the investment may be experienced.
Countries
  • Costa Rica
Geographic location where the impacts of the investment may be experienced.
Specific Location
San Jose de Costa Rica
Whenever identified, the area within countries where the impacts of the investment may be experienced. Exact locations of projects may not be identified fully or at all in project documents. Please review updated project documents and community-led assessments.
Financial Institutions
  • European Investment Bank (EIB)
International, regional and national development finance institutions. Many of these banks have a public interest mission, such as poverty reduction.
Project Status
Proposed
Stage of the project cycle. Stages vary by development bank and can include: pending, approval, implementation, and closed or completed.
Bank Risk Rating
U
Environmental and social categorization assessed by the development bank as a measure of the planned project’s environmental and social impacts. A higher risk rating may require more due diligence to limit or avoid harm to people and the environment. For example, "A" or "B" are risk categories where "A" represents the highest amount of risk. Results will include projects that specifically recorded a rating, all other projects are marked ‘U’ for "Undisclosed."
Borrower
Government of Costa Rica
A public entity (government or state-owned) provided with funds or financial support to manage and/or implement a project.
Sectors
  • Transport
The service or industry focus of the investment. A project can have several sectors.
Investment Type(s)
Loan
The categories of the bank investment: loan, grant, guarantee, technical assistance, advisory services, equity and fund.
Investment Amount (USD)
$ 280.06 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported 250
Converted using 2024-08-23 exchange rate.
Loan Amount (USD)
$ 280.06 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported EUR 250 million
Converted using 2024-08-23 exchange rate.
Project Cost (USD)
$ 952.22 million
Value listed on project documents at time of disclosure. If necessary, this amount is converted to USD ($) on the date of disclosure. Please review updated project documents for more information.
Currency conversion note:
Bank reported EUR 850 million
Converted using 2024-08-23 exchange rate.
Primary Source

Original disclosure @ EIB website

Updated in EWS Sep 30, 2024

Disclosed by Bank Aug 23, 2024


Contribute Information
Can you contribute information about this project?
Contact the EWS Team

Project Description
If provided by the financial institution, the Early Warning System Team writes a short summary describing the purported development objective of the project and project components. Review the complete project documentation for a detailed description.

According to the EIB, the project consists of the electrification and rehabilitation of a rail corridor comprising of two lines and about 50 km across the metropolitan area of San Jose de Costa Rica to run tram-train services. The project is a flagship initiative of the Global Gateway Investment Agenda.

Overall, the project is expected to contribute to climate change mitigation and pollution prevention. The project is also expected to bring social benefits in terms of improving mobility, especially for people without access to motorised private transport.

The EIB operation aims to finance the electrification, rehabilitation, and upgrade of the railway system of the great metropolitan area of San Jose (Costa Rica) as well as the acquisition of new electric trains. The project is a flagship initiative of the Global Gateway Investment Agenda.

Co-financing with the Central America Bank of Economic Integration (CABEI) and the Green Climate Fund (GCF), the project will optimise frequencies, electrify and rebuild infrastructure, improve crossings, modernise tracks, signalling, crossing areas or traffic control systems which in turn will improve the quality of life of the population of the metropolitan area with modern, accessible, and safe transportation.

Early Warning System Project Analysis
For a project with severe or irreversible impacts to local community and natural resources, the Early Warning System Team may conduct a thorough analysis regarding its potential impacts to human and environmental rights.

As stated by the EIB, concerning the social impacts, the project may require resettlement of some households and businesses.

Investment Description
Here you can find a list of individual development financial institutions that finance the project.

Contact Information
This section aims to support the local communities and local CSO to get to know which stakeholders are involved in a project with their roles and responsibilities. If available, there may be a complaint office for the respective bank which operates independently to receive and determine violations in policy and practice. Independent Accountability Mechanisms receive and respond to complaints. Most Independent Accountability Mechanisms offer two functions for addressing complaints: dispute resolution and compliance review.

No project contacts provided at the time of disclosure.

ACCESS TO INFORMATION

You can submit an information request for project information at: https://www.eib.org/en/infocentre/registers/request-form/request-form-default.htm

ACCOUNTABILITY MECHANISM OF EIB

The EIB Complaints Mechanism is designed to facilitate and handle complaints against the EIB by individuals, organizations or corporations affected by EIB activities. When exercising the right to lodge a complaint against the EIB, any member of the public has access to a two-tier procedure, one internal - the Complaints Mechanism Office - and one external - the European Ombudsman. A complaint can be lodged via a written communication addressed to the Secretary General of the EIB, via email to the dedicated email address: complaints@eib.org, by completing the online complaint form available at the following address: http://www.eib.org/complaints/form via fax or delivered directly to the EIB Complaints Mechanism Division, any EIB local representation office or any EIB staff. For further details, check: http://www.eib.org/attachments/strategies/complaints_mechanism_policy_en.pdf

When dissatisfied with a complaint to the EIB Complaints Mechanism, citizens can then turn towards the European Ombudsman. A memorandum of Understanding has been signed between the EIB and the European Ombudsman establishes that citizens (even outside of the EU if the Ombudsman finds their complaint justified) can turn towards the Ombudsman on issues related to 'maladministration' by the EIB. Note that before going to the Ombudsman, an attempt must be made to resolve the case by contacting the EIB. In addition, the complaint must be made within two years of the date when the facts on which your complaint is based became known to you. You can write to the Ombudsman in any of the languages of the European Union. Additional details, including filing requirements and complaint forms, are available at: http://www.ombudsman.europa.eu/atyourservice/interactiveguide.faces

How it works

How it works