As stated by the AIIB, the Project aims to boost Pakistan's national grid resilience against operational disturbances, expand south-to-north transmission capacity, optimize generation resource utilization, lower consumer power costs, and modernize the transmission network to reliably serve present and future electricity demand.
The proposed AIIB Project is part of the first phase of the Boosting Energy Security through Transmission in Pakistan (BEST-PAK) Multiphase Programmatic Approach (MPA) of the World Bank (WB). The WB MPA, with a total program envelope of USD 2,712.9 million, comprises four phases:
Implemented by the National Grid Company (NGC), the Project supports the installation of reactive power compensation devices to tackle critical grid stability challenges, including system reliability constraints and enabling full-scale integration of Variable Renewable Energy (VRE). It also includes technical assistance (TA) for Project delivery and preparation of subsequent phases under the WB's MPA. In detail, this Project consists of:
Total Project Cost: USD694.8 million
Financing Plan:
As stated by Devex, National Transmission & Dispatch Company (NTDC) was incorporated on 6th November, 1998 and commenced commercial operation on 24th December, 1998. It was organized to take over all the propertise, rights and assets obligations and liabilities of 220 KV and 500KV Grid Stations and Transmission Lines/Network owned by Pakistan Water and Power Development Authority (WAPDA). NTDC operates and maintains fourteen 500 KV and thirty eight 220 KV Grid Stations, 5110.48 km of 500 KV transmission line and 9686.32 km of 220 KV transmission line in Pakistan.
| Private Actor 1 | Private Actor 1 Role | Private Actor 1 Sector | Relation | Private Actor 2 | Private Actor 2 Role | Private Actor 2 Sector |
|---|---|---|---|---|---|---|
| - | - | - | - | National Grid Company of Pakistan Limited | Contractor | Energy |
AIIB Team Leader:
Jianshi Yao - Senior Investment Officer
Email: Jianshi.yao@aiib.org
World Bank Team Leader:
Mohammad Anis - Senior Energy Specialist
Email: manis@worldbank.org
Borrower - Government of the Islamic Republic of Pakistan:
Abbas Khan - Senior Joint Secretary, Ministry of Economic Affairs, Government of Pakistan
Email: comisb@hotmail.com
Contractor - National Grid Company, Pakistan:
Sohail Bajwa - Executive Director (Strategic Asset Planning), National Grid Company of Pakistan
Email: sohailbajwa@ntdc.com.pk
ACCESS TO INFORMATION
You can submit an information request for project information at: https://www.aiib.org/en/contact/information-request/index.html
ACCOUNTABILITY MECHANISM OF AIIB
The AIIB has established the Accountability Mechanism for Project-Affected People (PPM). The PPM provides Òan opportunity for an independent and impartial review of submissions from Project-affected people who believe they have been or are likely to be adversely affected by AIIBÕs failure to implement the ESP in situations when their concerns cannot be addressed satisfactorily through Project level GRMs or AIIB Management processes.Ó Two or more project-affected people can file a complaint. Under the current AIIB policy, when the bank co-finances a project with another development bank, it may apply the other bank's standards. You can refer to the Project Summary Information document to find out which standards apply. You can learn more about the PPM and how to file a complaint at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/how-we-assist-you/index.html
The complaint submission form can be accessed in Arabic, Bahasa Indonesia, Bengali, Chinese, English, Tagalog, Hindi, Nepali, Russian, Turkish, or Urdu. The submission form can be found at: https://www.aiib.org/en/about-aiib/who-we-are/project-affected-peoples-mechanism/submission/index.html